Risk: Agreement delayed / production dates push into busy season
Potential Impact: Integration work competing with regular work at busiest time of the year for sales, production, and fulfillment.
Mitigation Plan: Make decision on transferring production into 2022 and fulfill all else from west coast
Potential Cost Impact: Rent costs for Company A, delayed realization of production efficiencies ...